Archive

Posts Tagged ‘temporary transformer’

Emergency Replacement Transformer for Failed Transformer

January 7th, 2011 Comments off

What do you do if your manufacturing company suddenly loses its main 5000 kva, 34.5 kv to 480 volt transformer? You have orders pending. And if you can’t fill them, a key account may go elsewhere. You have employees suddenly out of work.  You need to heat the buildings.  And you are told it will take 10 weeks to get a new replacement transformer. This is one of a manufacturer’s worse nightmares. What to do? This happens more frequently than one may realize. MIDWEST actually recommends a “Disaster Action Plan,” on the shelf, ready to go, in case of such a nightmare.

 

MIDWEST receives these calls all too frequently. You might be fortunate and MIDWEST have a replacement reconditioned or used 5000 kva transformer that can be shipped immediately. No one has new transformers this size in stock. And many companies will not accept anything but a new replacement power transformer. In that case, the best solution is to rent a temporary transformer that will provide power until a new replacement transformer can be specified and manufactured. A new replacement transformer may take 10 weeks.

 

Renting transformers, and other electrical equipment, is a common solution to this critical problem. The first big question to ask when such an emergency occurs is, “Do you want power back on permanently as quickly as possible or do you just want power back on as quickly as possible?”  There is a huge difference in the time to perform either of these solutions. And way too often there is the presumption that one just must get power back on permanently. This presumption continues until the customer realizes how long it will actually take. Meanwhile many hours, even days, are wasted by chasing the wrong solution.

 

So the most critical event is to decide how fast one wants power restored.  MIDWEST has transformers, temporary high voltage cables and low voltage cables, and switches in stock.  But, more important, is the knowledge that temporary power installations can be a life saver for a facility that is suddenly down.

Pad Mount Transformer ─ Real Life Stories

May 12th, 2010 Comments off

The best test to predict the reliable operating condition of an oil filled transformer is the combustible gas-in-oil analysis. Using a syringe, 40 cc of oil is taken from the transformer and analyzed. When threshold levels of specific gases in the oil are reached, protocol demands appropriate action be taken.  This is an extreme oversimplification of a combustible gas-in-oil analysis.

 

One such case involved a 3000 kva, 25 kv primary, 600 volt secondary, foundry furnace transformer.  The oil test results indicated the transformer began generating high levels of acetylene.  Additional tests were performed and the transformer was shut down and taken out of service. A temporary transformer was put in its place to continue plant production. The defective transformer was sent out to be rebuilt.

 

Furnace transformers are special breeds of cats, designed to withstand the stresses of heavy shifting loads. Often times these transformers are pushed to the max in terms of load limits. Based on secondary ampere readings, this transformer was pushed to over 100% of rated load capacity, creating high thresholds of heat in the windings. Transformers don’t much like that too well. Heat puts all kinds of funny stresses on the internals of transformers.

 

In two months time the rebuilt transformer was put back in service and life continued on.